Project Details

Client:
SPDC
Project Name:
BONNY EMERGENCY RESPONSE SYSTEM PROJECT
Location:
BONNY OIL AND GAS TERMINAL, BONNY
Year Completed:
2018
Category:
Bonny

Project Overview

VESSELS DEPLOYED:
Tug boats: MV LOLO I
MV SOMKE
Ramp barges: STRIDES B2
MV IBHADE 1
SCOPE OF WORK:
• Fabrication and installation of of 20’’ pipeline – 1000m fire line
• Unbolting of existing/ bolting of newly installed line
• Hydro testing of newly welded 20’’ line (1000m) long.
• Excavation work / In-situ construction of concrete supports.
• By-passing of 48’’ line through a rupture disc to the 20’’ line.
• Hook up newly installed line to tank

DURATION: 10 months
STATUS: Completed