Project Details
SPDC
FYIP 5 OIL WELLS COMPLETION WORKS
CLUSTER 5A – FORCADOS ESTUARY OFFSHORE OIL FIELD
–
2015
Estuary
Project Overview
VESSELS DEPLOYED: –
SEWOPS: MV Tiger Shark
MV Black Jack
EMERGENCY RESPONSE VESSEL: MV Thethis
SECURITY VESSEL: MV Rhema Star
CREW BOAT: MV Joetek Azaebi
SCOPE OF WORK
• Fabrication, NDT, and installation of all topside piping spools.
• Hook up of already installed bulkline, and #1 bulkline riser to topside.
• Conversion of all actuated choke valves to manual.
• Replacement of corroded and missing bolts, nuts with PTFE coated bolts and nuts
• Replacement of dummy and missing spools on the topside.
• Grit blasting and painting of the entire cluster structures.
• Complete pre-commissioning and N2 inerting to 3bar.
• Subsea diving operations for the inspection of riser clamps and flanges.
DIVING SUPPORT SUBCONTRACTOR: Subtech Offshore Services Nigeria Ltd
(James Fisher Subtech Group)
SMART FLANGE CONNECTORS SUPPLIER: Oceaneering/Craymond Nigeria Ltd
DURATION: 2 Months.
STATUS: Completed